Cost Approach (2024)

Step-by-Step Guide to Understanding the Cost Approach Appraisal in Real Estate

Last Updated February 20, 2024

What is Cost Approach?

The Cost Approach is a real estate appraisal method that estimates a property’s valuation based on the cost to replace or reconstruct the property, minus accumulated depreciation.

Cost Approach (1)

Table of Contents

  • How Does the Cost Approach Appraisal Work?
  • How to Calculate Property Value with the Cost Approach
  • Cost Approach Formula
  • Cost Approach Calculator
  • Cost Approach Calculation Example

How Does the Cost Approach Appraisal Work?

The cost approach is among one of the three main approaches used in practice to appraise the value of real estate properties.

The two other valuation methods frequently used are the income approach and the sales comparison approach. Contrary to the other approaches, the cost approach is far less reliant on the active real estate market (and any data on comparable assets).

Simply put, the cost approach estimates the value of a property based on the total cost expected to be incurred under the hypothetical pretense that the property was destroyed and needed to be reconstructed.

Therefore, the cost approach estimates the value of a property based on the value of the underlying land on which the property was constructed, the replacement (or reproduction) cost, and the accumulated depreciation of the improvements.

Briefly put, the question answered here is, “How much would it cost in total to reconstruct and rebuild the property from the ground up?”

The utility of the cost approach method stands out among the three main appraisal methods for properties when there is no (or very limited) market data on comparable properties. Hence, the cost approach is often the only viable option available in such instances.

The premise of the cost approach, or “replacement cost,” is the principle of substitution, which states that no rational investor should pay more for a property than the cost of constructing an equivalent substitute.

Estimating the property cost in this case is essentially determining the total spending required to rebuild the property from the ground up, which is then compared to the current asking price:

  • Replacement Cost < Asking Price → Current Pricing is Potentially Reasonable
  • Replacement Cost > Asking Price → Current Pricing is NOT Reasonable

How to Calculate Property Value with the Cost Approach

The steps to appraise the value of a property using the cost approach method are as follows.

  1. Estimate Land Value → Estimate the value of the land by analyzing recent sale data on comparable, vacant land parcels. Based on the characteristics of the subject project, discretionary adjustments most likely must be applied to factor in the differences.
  2. Estimate Replacement Cost of Improvements → Estimate the cost to reconstruct the property and improvements, inclusive of direct and indirect costs such as materials, labor, construction, contractor fees, permits, administrative fees, financing costs, professional fees, insurance, etc. Most often, either the square foot method or the unit-in-place method is used here.
  3. Estimate Accumulated Depreciation → Estimate the depreciation expense, which pertains to the losses in property value from age, wear and tear, deterioration in building components, functional obsolescence, and external obsolescence.
  4. Calculate Sum of Land Value and Depreciated Improvement Cost → The implied property value under the cost approach method equals the estimated land value, net of the accumulated depreciation cost tied to the improvements.

The Wharton Online
and Wall Street Prep Real Estate Investing & Analysis Certificate Program

Level up your real estate investing career. Enrollment is open for the Sep. 9 - Nov. 10 Wharton Certificate Program cohort.

Enroll Today

Cost Approach Formula

The formula for the cost approach method to perform a real estate appraisal is as follows.

Property Value = Land Value + (Cost New Accumulated Depreciation)

Where:

  • Land Value → The estimated value of the land by itself, based on recent comparable sales data.
  • Cost New → The cost expected to be incurred if the property was reconstructed to a nearly identical state as of the present date.
  • Accumulated Depreciation → The total depreciation to date from all sources, i.e. physical depreciation, functional obsolescence, and external obsolescence.

To briefly elaborate on the “Cost New” input in the formula, there are two distinct definitions to take note of:

  • Replacement Cost New → The replacement cost is the current amount it would cost to rebuild a property using current standards for construction material, layout, and design.
  • Reproduction Cost New → In contrast, the reproduction cost is the cost to rebuild the property using identical materials, design, and standards that were in place on the date of the initial construction.

While the relative difference between the replacement and reproduction cost is marginal for modern, recently built properties, the difference in the cost can be material for historical, outdated properties, or unique real estate assets.

Further, there are three forms of depreciation recognized in real estate appraisals:

  • Physical Deterioration → The tangible losses in property value from the “wear and tear” starting from the initial date on which the construction was completed.
  • Functional Obsolescence → The losses in the market value of a property due to factors such as subjective consumer preferences, technological innovations, or unfavorable shifts in market standards.
  • Economic Obsolescence → The losses in property value caused by external factors that pertain to the property’s location, such as the local economy and environment.

Cost Approach Calculator

We’ll now move to a modeling exercise, which you can access by filling out the form below.

Cost Approach Calculation Example

Suppose a real estate appraiser is tasked with estimating the value of a residential property using the cost approach.

Based on the data collected on land sales of comparable size and in a nearby location, the appraiser estimates the land on which the residential property stands to be currently worth around $100k.

  • Land Cost = $100,000

Using the comparative unit method, a form of analysis to determine the cost of construction on a square footage basis (and with consideration toward the construction and material type, as well as quality), the appraiser prices the cost at $120 per sq. ft.

  • Cost per Square Foot (sq. ft.) = $120

If we assume the building is $25k sq. ft. in total, the cost new is $3 million.

  • Property Size = 25,000 sq. ft.
  • Cost New = $120 × 25,000 sq. ft. = $3 million

The economic useful life of the improvements is estimated to be 50 years with 40 years remaining.

The age-life method of depreciation, assuming straight-line depreciation and a salvage value of zero, implies that the improvements must be depreciated by 20.0%.

  • Depreciation Deduction (% Aged) = 1 – (40 Years ÷ 50 Years) = 20.0%

After applying the depreciation deduction of 20.0% to the cost new of $3 million, the accumulated depreciation amounts to $600k.

  • Accumulated Depreciation = 20.0% × $3 million = $600,000

In closing, the final step is to add the land cost to the depreciation-adjusted cost new to arrive at $2.5 million for the value of the residential property per the cost approach.

  • Property Value = $100k + $3 million – $600k = $2.5 million

Cost Approach (8)

Comments

0 Comments

Inline Feedbacks

View all comments

Cost Approach (2024)

FAQs

What is the cost approach? ›

The cost approach is a real estate valuation method that estimates the price a buyer should pay for a piece of property is equal the cost to build an equivalent building. In the cost approach, the property's value is equal to the cost of land, plus total costs of construction, less depreciation.

What are the four steps in the cost approach? ›

Basic steps in the cost approach are:
  • Estimate the value of the land as if vacant.
  • Estimate the replacement cost new of the improvements.
  • Estimate the loss in value from all forms of depreciation.
  • Deduct the total amount of depreciation from the replacement cost new.
  • Estimate the same amount for any other improvements.

What is the process cost approach? ›

It calculates the average cost per unit by spreading the total production costs evenly over all units produced during a specific period. It provides a standardized cost for each unit. This method simplifies cost tracking for hom*ogenous products but may not account for variations in individual unit costs.

What is the basic approach of cost? ›

The cost approach is based on the logic that informed buyers will not pay more for a property than it will cost them to build to a similar property from scratch and with the same level of utility. The cost approach is appropriate for unique properties, such as churches or schools with unique components.

What is the cost to cost approach? ›

The cost-to-cost method is a way to recognize revenue and profit in long-term projects based on the percentage of completion of the project. It's commonly used in industries such as construction, aerospace, and defense where projects span multiple accounting periods.

What is the total cost approach? ›

Total Cost Approach. The total cost method normally consists of subtracting bid price from the actual cost of performance and adding profit to the resulting amount.

What is the cost based approach? ›

Cost-based pricing is a pricing strategy where businesses set a selling price based on a product's production, manufacturing, and distribution costs. Typically, they arrive at this figure by adding a markup percentage to the total cost of making and delivering the product.

What is the process costing approach? ›

What is a process costing system? A process costing system is a method typically used within certain sectors of the manufacturing industry to determine the total production cost for each unit of product. It accumulates cost from each process or department and allocates them to the individual products produced.

What is cost principle approach? ›

The concept of cost principle is one of the five Generally Accepted Accounting Procedures (GAAP), which is established by the Financial Accounting Standards Board (FASB). The purpose of cost principle is to easily identify the original value of an asset on financial documents.

What is full cost approach? ›

Full costing, or absorption costing, accounts for all costs, both fixed and variable along with overhead, that go into a finished product. Advantages of full costing include compliance with reporting rules and greater transparency.

What is standard cost approach? ›

Standard costing is the practice of estimating expenses in the production process since manufacturers cannot predict actual costs in advance. Manufacturers use this methodology to plan upcoming costs of various expenses, such as labour, materials, production and overhead.

What is the cost strategy approach? ›

Cost strategy is built on no-frills. Cost leadership strives towards cutting costs to a minimum possible levels in order to provide customers with lower prices and thus boost their savings.

What is the cost approach Quizlet? ›

Cost Approach. The cost approach is based on the proposition that the informed purchaser would pay no more for the subject than the cost to produce a substitute property with equivalent utility.

What is the cost approach in production planning? ›

The conventional approach to planning production is to start with the goods and services that a firm intends to provide and then decide what production configuration will achieve the intended output at the lowest cost. This is the cost approach to production planning.

What is the cost approach in Uspap? ›

The Cost Approach is a real estate appraisal method that estimates a property's valuation based on the cost to replace or reconstruct the property, minus accumulated depreciation.

What is the cost asset approach? ›

The cost approach is one of three generally accepted intangible asset valuation approaches. The cost approach may be particularly applicable to the fair value measurement of certain types of intangible assets.

References

Top Articles
Latest Posts
Article information

Author: Zonia Mosciski DO

Last Updated:

Views: 5636

Rating: 4 / 5 (51 voted)

Reviews: 82% of readers found this page helpful

Author information

Name: Zonia Mosciski DO

Birthday: 1996-05-16

Address: Suite 228 919 Deana Ford, Lake Meridithberg, NE 60017-4257

Phone: +2613987384138

Job: Chief Retail Officer

Hobby: Tai chi, Dowsing, Poi, Letterboxing, Watching movies, Video gaming, Singing

Introduction: My name is Zonia Mosciski DO, I am a enchanting, joyous, lovely, successful, hilarious, tender, outstanding person who loves writing and wants to share my knowledge and understanding with you.